A Lin Hydropower Project


02:35' CH-04, 04/04/2014

This is the second largest hydropower project in the North Central area, it is expected to make active contribution to the course of construction and development of economy of Thua Thien Hue province in particular and the country in general.

The project is constructed at Alin river and Bo river system in Phong Xuan commune (Phong Dien district), Hong Trung and Hong Van communes (A Luoi district) with total capacity of 62MW consisting of two steps (step 1 with capacity of 42MW, step 2 with capacity of 20MW).

As expected, the project will provide an annual average production of over 268.49 million KWh for the national electric grid, as well as contribute to regulate flow discharge to supply domestic water and mitigate flood for downstream area.

Alin B1 hydropower project is located in Hong Trung, Hong Van communes, A Luoi and Phong Dien districts, Thua Thien Hue province, the project is owned by Truong Phu Hydropower Joint-stock Company in the term of Build-Own-Operation (BOO). The project was approved by the Ministry of Industry and Trade in the official document No. 6902/BCT-NL dated 17-07-2009 on adjustment and additional planning of small hydropower projects in Thua Thien Hue province.

Major task of A Lin B1 hydropower project: Generating with installed capacity of 42 MW, connecting to local electric grid with voltage of 110KV.

Design standard:

According to the Vietnamese standard TCXDVN 285:2002 “Hydraulic works - Major design regulations'', if A Lin B1 project consists of 1 plant with capacity N>50MW, it is classified as grade II work, its design standards area as follows:

- Design flood, P = 0.5%.
- Check flood, P = 0.1%.
- Power generation with firm frequency P = 90%.
- Construction flood, P = 5%, P = 10%.
If the project consists of 2 plants with capacity N<50MW, it is classified as grade II work, its design standards are as follows:

- Design flood, P = 1%.
- Check flood, P = 0.2%.
- Power generation with firm frequency P = 85%.
- Construction flood, P = 5%, P = 10%.
Related documents:

Documents related to preparation of the project include:

- The Vietnamese construction standard TCXDVN 285:2002 “Hydraulic works - Major design regulations”.

- The Decision No. 709/QĐ-NLDK dated 13/4/2004 of Ministry of Industry on financial economic calculation for hydropower projects.

- The Decision No. 2014/QĐ-BCN dated 13/6/2007 of Ministry of Industry on temporary regulation of investment financial economic calculation and analysis contents and frame of electric sale price of power projects.

- The Decree No. 164/2003/NĐ-CP dated 22/12/2003 of the Government on income tax of enterprises.
- The Circular No. 42/2007/TT-BTC dated 27/4/2007 of Ministry of Finance on detailed regulations of realization of State Law on resources tax.

- General Outline of Investigation and Design of Alin hydropower project No. No.657C-TH-ĐC01 No.657C-TH-ĐC02.

- Quality management system ISO 9001:2000 of HEC.

- Other related standards and documents.

Total hits 280  -  Last update 04/04/2014 02:37' CH

Tài nguyên

© 2012 Vietnam Hydraulic Engineering Consultants Corporation - JSC.
Address: 95/2 Chua Boc Street, Dong Da District, Hanoi - Tel: (04) 3852-6285 - Fax: (04) 3563-2169
Chief Editor: Vo Van Lung - Deputy Director General

Visit Total: .
Visitor Online: .
Sponsor links (Provided by VIEPortal.net - The web cloud services for enterprises)
Thiết kế web, Thiết kế website, Thiết kế website công ty, Dịch vụ thiết kế website, Dịch vụ thiết kế web tối ưu, Giải pháp portal cổng thông tin, Xây dựng website doanh nghiệp, Dịch vụ web bán hàng trực tuyến, Giải pháp thương mại điện tử, Phần mềm dịch vụ web, Phần mềm quản trị tác nghiệp nội bộ công ty,