Cua Dat Reservoir
Project location: Chu river - Thuong Xuan district, Thanh Hoaprovince Construction time: Investigation and design time: 1999-2004 Commencement time: 02/02/2004 Project managers:Dinh Xuan Tu, Le Van Ngo, Le Manh Hiep, Hoang Minh Dzung, Vo Van Lung Major technical parameters: - Work grade: I - Catchmentarea: 5938 km2 - Normal water level (NWL): 110 m - Dead water level (DWL): 73 m - Total storage capacity: 1,450 million m3 - Effective storage capacity: 793.70million m3 - Dead storage capacity: 268.69million m3 Scale and structure of the project works Project tasks: + Mitigating flood with P=0.6% + Creating stable irrigation source for 86,862 ha + Supplying water to domestic and industrial uses with Q=7.715m3/s + Generating power with N = 97 MW + Supplementing water for downstream of Ma river in dryseason to prevent saline intrusion, improve ecological environment with Q=30.42m3/s + Main dam:Concreteface rockfill dam (CFRD), L=949.92m, Hmax=118.50m and 2 auxiliary dams + Spillway
+ Powerhouse: - Number of unit: 2 - Installed capacity: 97 MW - Capacity of 1 unit: 48.5 MW - Maximum head (Hmax): 89.4m - Minimum head (Hmin): 45.7m - Design head (Hdesign): 69.3m Total hits 74 - Last update 25/02/2014 01:33' CH |
|