Long Song ReservoirProject location: Long Song river, Binh Thuan province Construction time: Commencement in 2001 Project managers: Le Van Ngo - Do Van Xung - Phan Van Luong Project tasks: Irrigating 4260 ha Major technical parameters: Basin area: 394 km2 Work grade: III Surcharge water level: + 77.63 m Normal water level: +76.95 m Dead water level: +54.00 m Total storage capacity: 36.88 million m3 Effective storage capacity: 32.28 million m3 Dead storage capacity: 3.6 million m3 Scale and structure of major works: - Gravity concrete dam + Dam crest elevation: +79.50, length: 246m, Hmax: 44.80m - Spillway: Ophiserov, gated, bucket type energy dissipator. Spillway dimension n(BxH) = 6x(8x6)m, Qrelief p=1%: 1795.3 m3/s. Spillway sill elevation: +70.95. - Non-pressure intake, dimension: 1.50 x 2.20m, Qdesign = 4.20 m3/s - Water convey system + R.C turnout + Channel: Long Song river of 4.4 km long, design discharge (Qdesign) = 2.68 m3/s + Tuy Tinh dam: constructed of rock masonry and rock gabion + Cay Ca canal constructed of R.C, 2 km long, design discharge (Qdesign) = 1.52 m3/s - Irrigation canal system + Cay Ca main canal (right bank), 11.97 km long, Q=1.5 m3/s and 14 primary canals, 27.85 km long + Tuy Tinh main canal (left bank), 9.12 km long, design discharge Q=2.35 m3/s and 10 primary canals, 15.96 km long. Total hits 50 - Last update 11/03/2014 03:12' CH |
|