Dinh Binh Hydropower Project

03:19' CH-18, 18/02/2014

Project location: on the left side of Kon river, at spillway span No.8 in Vinh Hao commune, Vinh Thanh district, Binh Dinh province.

Project manager: Nguyen Xuan Uc

Project tasks:

- Generating power with capacity of 6600KW

- Controlling early, late floods

- Mitigating flood, supplying water for industrial and domestic uses

- Supplying irrigation water to agricultural production, rural industries and domestic uses

Major technical parameters:

Work grade: III

Technical parameters of the powerhouse:

+ Minimum discharge through 1 unit: Qmin=9.78 m3/s

+ Maximum discharge through 1 unit: Qmax=12.5 m3/s

+ Design head: Hdesign = 30.74m

+ Installed capacity: N = 6.6MW

+ Number of unit: 2 units

+ Turbine type: Francis turbine

+ Vertical axis 3-phase synchronous generator

+ Annual average power output: 32.22 million KW

Sponsor links (Provided by VIEPortal.net - The web cloud services for enterprises)
Thiết kế web, Thiết kế website, Thiết kế website công ty, Dịch vụ thiết kế website, Dịch vụ thiết kế web tối ưu, Giải pháp portal cổng thông tin, Xây dựng website doanh nghiệp, Dịch vụ web bán hàng trực tuyến, Giải pháp thương mại điện tử, Phần mềm dịch vụ web, Phần mềm quản trị tác nghiệp nội bộ công ty,