Dinh Binh Hydropower ProjectProject location: on the left side of Kon river, at spillway span No.8 in Vinh Hao commune, Vinh Thanh district, Binh Dinh province. Project manager: Nguyen Xuan Uc Project tasks: - Generating power with capacity of 6600KW - Controlling early, late floods - Mitigating flood, supplying water for industrial and domestic uses - Supplying irrigation water to agricultural production, rural industries and domestic uses Major technical parameters: Work grade: III Technical parameters of the powerhouse: + Minimum discharge through 1 unit: Qmin=9.78 m3/s + Maximum discharge through 1 unit: Qmax=12.5 m3/s + Design head: Hdesign = 30.74m + Installed capacity: N = 6.6MW + Number of unit: 2 units + Turbine type: Francis turbine + Vertical axis 3-phase synchronous generator + Annual average power output: 32.22 million KW Total hits 58 - Last update 19/02/2014 02:36' CH |
|